Mexico has a geographic advantage that should draw AI data centers. It borders the United States, and data can reach American users almost as fast as it can from inside the country. Still, power shortages and a slow permit system are holding the country back, Bloomberg reported.

Mexico has 71 of the more than 500 data centers in Latin America, according to Data Center Map, which Bloomberg cited. Brazil has 225. Chile, a much smaller country, has 66.

Economy Minister Marcelo Ebrard told Bloomberg that private companies are already building power plants and power lines for some of the announced projects. He framed the issue as a simple choice for the country. “There are only two options: Either you have it, or you don’t,” Ebrard said.

How long does it take to get power for a data center in Mexico?

Investors describe long delays. CloudHQ announced a $4.8 billion plan last year for six data centers in Querétaro. The company has applied for about 111 permits, not counting energy-related ones. Luis Lugo, CloudHQ’s top executive in Mexico, told Bloomberg that getting an electricity connection contract takes at least eight months under normal circumstances. He said the process can take up to three years.

Why are power shortages holding back AI data centers in Mexico?

The bottleneck is tied to how Mexico generates and distributes power. President Claudia Sheinbaum plans to add about 32 gigawatts of new capacity by 2030. By law, the state utility CFE must produce most of that power, which Bloomberg said limits private investment. Mexico also relies heavily on natural gas. The government wants 38% of its electricity to come from renewable sources by 2030, up from about a quarter today. The industry group MEXDC says more green power is needed to win over technology firms that have climate goals.

Querétaro hosts about 70% of Mexico’s data centers, including sites run by Amazon Web Services and Google. But its grid was not built to serve such heavy users. “The Querétaro area is already very saturated,” Juan Carlos Mondragón, head of MEXDC, told Bloomberg.

MEXDC expects just over $20 billion in direct investment over the next four years. Bloomberg contrasted that figure with Moody’s estimate that U.S. data center spending will reach $700 billion this year.